All:
See below:

1. Concept Plan goes first
2. Site Plan goes second. They are usually handles at the same time 3. Construction Plans follow after approval from Concept and Site

Looking for approval of Concept and Site by March 1. CDs to follow. Only staff review. 30-60 days likely. TDEP – local review after City Stamps.

Fees/Permits/special assessments (water) to follow. We need to do an ownership change of the permit in order to get mass grading. Could come prior to purchase of the property. Need to check with Bryce about that.

Will need to bond the public water and sewer after connected. Maybe need to do the same of R.O.W., but that is not known.

We are looking at variances – height, parking (1.1 per bedroom). There are restrictions against type of siding. Seems there is a problem with vinyl siding.

Looks like we have to meet design guidelines for the Town (remember Westminster?). Fire protection needed before prairie building? Need to investigate that.
Need pump station. $1000 per door
Off-site improvements? Traffic study being performed.

Amenities to be investigated: Clubhouse, Pool, Dog Park, Pavilion, Pickleball Courts, Volleyball, Fire Pits, Walking Trail on plan.