List below are the revised terms of the LOI:
Clean Phase 1 Completed July 13th, 2022
Clean Title Completed July 2022
ALTA Survey Will be Complete December 16th, 2022
Topo Survey Completed April 2022
Water, Sewer, and Power will serve letters Will have January 2022
Geotech Completed August 22nd, 2022
Environmental items done i.e. wetlands, etc. if applicable Completed July 22nd, 2022. There are no impacts on streams or wetlands there for no Permit is needed.
Site plan approval Concept Plan will be submitted December 26th, 2022, for a January 31st, 2023, Approval
Site Plan ( 90% full CDs ) will be submitted January 30th, 2023 for a February 28th, 2023 Approval. Need Vertical footprints for this. 2 Month Process
Grading permit Mass Grading Plan is completed, will submit to TDEC (Tennessee Department of Environmental Conservation) for a NOI (Notice of Intent) in January for a February Approved of a NOC (Notice of Coverage). See attached Email for Kyle Brown City of La VergeneAssistant City Administrator that states a Mass Grading Plan and Erosion Control Plan (Part of NOC Approval) a Grading Permit can be obtained.
Construction Drawing Horizontal and Vertical – Horizontal and Vertical CDs can be submitted for permit immediately after Site Plan approval. 45-60 day turnaround.
DOT sign off-usually can’t get grading permit without this now but depends on municipality
Waldron Road is a City Road and does not need DOT Approval.
Thank You,
Engineering and Utilities look at Horizontal after site plan approval – 3 Month process
Vertical can start at Site plan approval
Probable participation fee for sewer outfall.