Northern Oaks
Atwell
. CLOMR
.. Required by Ocala in advance of work
.. City must sign before submission to FEMA
.. Revises
.. Done with submission of site plan
.. Submitted to FEMA
… City must sign the MT1 or MT2 form with submission
… Take 6 months with FEMA
.. Permit fee about $2500
… Atwell to confirm
. ERP
. Site Plan
. Once City and WMD approve, work can begin
. FEMA approval required before vertical permits
. Traffic Study
.. Methodology ubmitted to and approved by City already
.. TIA must be submitted to County
.. Atwell: Phased or all at once
.. Mazzie: Depends on cost impact or possibility of changes over time
.. Atwell: Ask Kittleson
.. Sinclar: TIA has been done as one Phase by Kittleson and will be done in a week
. Construction Entrance
.. Atwell will identify a location
.. Construction and non-construction traffic can’t mix
. Phase plan needed
.. Atwell to draft something to show us and then City
.. REW will send suggestions to Atwell
. Fire Hydrant Flow Test
.. Damon sent invoice for $750
.. Needs Burkentine approval
.. Can get done next week
.. MT and KG will handle getting it approved
. Borings
. Landscape Architecture
.. Does tree mitigation calculations too
.. Mazzie and REW agree limiting to Burkentine Phase
. Surveyor
. Surveyor picked up trees so no survey for that needed
. MB has requested quotes from Architects for elevations
. 20% open space required
. Southern Waters will continue moving TIA forward and discuss cost sharing
. Atwell planning for 20’ buffer, but fence will be required
.. 25’ buffer eliminates fence
… Might help open space too
… Atwell thinks it would fit
.. Atwell thinks buffer is open space
.. Buffers must be planted
. Atwell hopes to know dirt balancing by next week
. Not doing a re-plat just a re-configuration
.. Avoids NIMBY objections
. Vinyl Siding
.. REW: Used?
.. Atwell: Rare because of heat
.. REW: Will City object?
.. Mazzie: Need pretty elevations and vinyl listed on application
. Conversation with City about Road Access
.. REW & RM: Start conversation next Thursday but make no promises
. Endangered Species
.. Report warned about various environmental issues
.. Needs to go into City with site plan
.. No wetlands
.. Mitigation plan for gopher tortoises required
… Done after City and ERP approval
.. No Eagle’s nests
.. ERP will go into City with site plan on 2/28
… Gets submitted to District — $5000 or cheaper
… 30-day review time
…. That’s after diligence period is over!
… Atwell: Assume 3 rounds of review — 4 months