All, please see below meeting minutes for 2/9/2023 regarding Northern Oaks Phase I (aka: The Stables).
As always, please add, edit, comment or ask questions at your discretion. Have a good day and thank you for your time.
Atwell Deliverables:
- Complete fire safety system design and service hookups (waiting on Burkentine for MEP and driveway orientation input, respectively)
RVi Deliverables:
- Prepare landscape plan/amenities for the 2/28/23 site plan submission (Atwell will us a basic footprint for now under the assumption it will be replaced with detailed design on submission 2)
Burkentine/Precipice Properties Deliverables:
- Determine if driveways can be “flipped”, which will determine how the service lines are laid out
- Provide MEP to Atwell for fire safety/sprinklers (i.e., line sizing)
- Determine the number of garbage compactors for phase I (8 yard limitation)
- Provide clubhouse design to RVi
SWC Deliverables:
- SWC to speak with Seller regarding well specifications to be relayed to Atwell.
- Reach out to surveyor regarding (i) specificity regarding City of Ocala’s easement and (ii) table for trees marked.
- SWC to speak with local counsel regarding technical process/requirements to close on phase 1.
General Notes:
- Lot Split process will require updated legal description, but should not be completed until second round of site submissions as we need to ensure the boundary line between Phase I and Phase II does not move due to comments, etc.
- Geotech being performed today. Expect preliminary results in about a week and final results no later than 2/28/23.