Northern Oaks

Atwell

. CLOMR

.. Required by Ocala in advance of work

.. City must sign before submission to FEMA

.. Revises 

.. Done with submission of site plan

.. Submitted to FEMA

… City must sign the MT1 or MT2 form with submission

… Take 6 months with FEMA

.. Permit fee about $2500

… Atwell to confirm

. ERP

. Site Plan

. Once City and WMD approve, work can begin

. FEMA approval required before vertical permits

. Traffic Study

.. Methodology ubmitted to and approved by City already

.. TIA must be submitted to County

.. Atwell:  Phased or all at once

.. Mazzie:  Depends on cost impact or possibility of changes over time

.. Atwell:  Ask Kittleson

.. Sinclar:  TIA has been done as one Phase by Kittleson and will be done in a week

. Construction Entrance

.. Atwell will identify a location

.. Construction and non-construction traffic can’t mix

. Phase plan needed

.. Atwell to draft something to show us and then City

.. REW will send suggestions to Atwell

. Fire Hydrant Flow Test

.. Damon sent invoice for $750

.. Needs Burkentine approval

.. Can get done next week

.. MT and KG will handle getting it approved

. Borings

. Landscape Architecture

.. Does tree mitigation calculations too

.. Mazzie and REW agree limiting to Burkentine Phase

. Surveyor

. Surveyor picked up trees so no survey for that needed

. MB has requested quotes from Architects for elevations

. 20% open space required

. Southern Waters will continue moving TIA forward and discuss cost sharing

. Atwell planning for 20’ buffer, but fence will be required

.. 25’ buffer eliminates fence

… Might help open space too

… Atwell thinks it would fit

.. Atwell thinks buffer is open space

.. Buffers must be planted

. Atwell hopes to know dirt balancing by next week

. Not doing a re-plat just a re-configuration

.. Avoids NIMBY objections

. Vinyl Siding

.. REW: Used?

.. Atwell:  Rare because of heat

.. REW: Will City object?

.. Mazzie:  Need pretty elevations and vinyl listed on application

. Conversation with City about Road Access

.. REW & RM: Start conversation next Thursday but make no promises

. Endangered Species

.. Report warned about various environmental issues

.. Needs to go into City with site plan

.. No wetlands

.. Mitigation plan for gopher tortoises required

… Done after City and ERP approval

.. No Eagle’s nests

.. ERP will go into City with site plan on 2/28

… Gets submitted to District — $5000 or cheaper

… 30-day review time

…. That’s after diligence period is over!

… Atwell: Assume 3 rounds of review — 4 months